Week 7
Welcome to meeting minutes page for GSoC 2025 at FOSSology 17-07-2025.
Attendees:
Missed:
General
- Shaheem Azmal M MD: General Updates regarding the project and new licenseDb release.
Updates from contributors
-
- Not availible last week because of the health issues.
- This week i will focus on integrating atarashi with fossology as a agent.
-
- No Update Available.
-
- Finished the implementation on scancode parallel-scanning implementation.
- improved the time by over 50%.
- Need to caution the user regarding the usage of resources. because it might kill the other agents.
- Shares screehshots of the previous and current scan time.
-
- I have been working on the agent part of text phrases project.
- The UI part finished and shows a short demo of current implementation.
-
- No Updates as there were some connection issues from users end.
-
- This week, I focused on handling PHP Composer dependencies required by Fossology and advancing the packaging process.
- After reviewing composer.json, I identified 10 dependencies that are not available as Debian packages.
- Filed ITPs (Intent To Package) for all created packages, following Debian policy and ensuring transparency in the packaging process. Here are the details
- I also sent an email update to the main Fossology ITP (ITP #924659), summarizing my progress and the status of the new dependency packages.
- Ensured that all 10 packages were built and installed successfully.
-
- This week we continued the migration of all current available progress so far in the demo repository into the main Safaa repository.
- We have made some adjestments in the code quality as well.
- Currently working on creating pipline for data training.
-
- Working on the pages like schedule analysis and upload page.
-
- Try to fully fix the database issue in the web pod
- Start testing the new build system using CMake
- Go through the Kubernetes files and clean up anything outdated
-
- Migration of all the pages is finished.
- Shows demo of migrated pages of FOSSologyUI project.