Week 06 Meetings and Activities
Integration of ORT with FOSSology Sync Meeting 6
(July 21, 2025)
Attendees
Discussion
- I was on exam leave for two weeks (July 7th–19th) and resumed regular project activity afterward.
- Had a sync meeting with my mentor to review ongoing tasks and next steps.
- Discussed feedback received from ORT maintainers regarding the NOMOS plugin — it was suggested to use a static release of NOMOS for easier integration and reproducibility.
- Mentor recommended learning about CI/CD pipelines, particularly GitHub Actions and how to publish GitHub Releases to support NOMOS distribution.
- I also informed the mentor that I have opened a pull request for my ongoing work in ORT Repository.
Progress
- During the week, some CI/CD checks failed on the ORT side after pushing changes.
- Worked on resolving CI/CD issues encountered in the ORT repository.
- Made code adjustments based on error messages and feedback from the maintainers.
- Started learning about GitHub Actions workflows and how to automate releases for NOMOS.
Next Steps
- Finalize the static NOMOS release setup for CI consumption.
- Set up an initial GitHub Actions workflow for building and releasing NOMOS binaries.
- Continue improving the NOMOS plugin's stability based on CI feedback.
Links
- Pull Request: oss-review-toolkit/ort#10631