Week 06 Meetings and Activities

Integration of ORT with FOSSology Sync Meeting 6

(July 21, 2025)

Attendees

Discussion

  • I was on exam leave for two weeks (July 7th–19th) and resumed regular project activity afterward.
  • Had a sync meeting with my mentor to review ongoing tasks and next steps.
  • Discussed feedback received from ORT maintainers regarding the NOMOS plugin — it was suggested to use a static release of NOMOS for easier integration and reproducibility.
  • Mentor recommended learning about CI/CD pipelines, particularly GitHub Actions and how to publish GitHub Releases to support NOMOS distribution.
  • I also informed the mentor that I have opened a pull request for my ongoing work in ORT Repository.

Progress

  • During the week, some CI/CD checks failed on the ORT side after pushing changes.
  • Worked on resolving CI/CD issues encountered in the ORT repository.
  • Made code adjustments based on error messages and feedback from the maintainers.
  • Started learning about GitHub Actions workflows and how to automate releases for NOMOS.

Next Steps

  • Finalize the static NOMOS release setup for CI consumption.
  • Set up an initial GitHub Actions workflow for building and releasing NOMOS binaries.
  • Continue improving the NOMOS plugin's stability based on CI feedback.