Week 11

(August 14, 2025 – August 20, 2025)

Meeting 1

Date: August 14, 2025

Attendees

Discussions

  • Reviewed feedback for the UI implementation of similar licenses and obligations.
  • Planned integration for the email messaging system.
  • Discussed pending PRs and review timelines.

Updates

  • Received review feedback for the UI implementation and implemented the requested changes.
  • Opened a new PR for the email messaging system, which is currently under review.
  • All active PRs — including UI, refresh token, and email messaging system — are under review, awaiting approvals.

Planning for Next Week

  • Wait for reviews and finalize the UI implementation PR.
  • Finalize the email messaging system once review comments are addressed.