Week 14–17

(September 8, 2025 – October 4, 2025)

Meeting

No meetings were held during this period due to mentor unavailability and mid-semester examinations.


Updates

  • No major work was done during these weeks as mid-semester exams were ongoing.
  • The GSoC 2025 closing ceremony for 12-week contributors took place during this time.
  • Mentor unavailability also affected review timelines and project discussions.
  • All major PRs have been submitted and are awaiting review.
  • The monorepo setup remains the only pending task for completion.

Planning for Next Week

  • Resume active development once exams conclude and mentor returns.
  • Finalize and merge the monorepo setup.
  • Complete any pending documentation and ensure all PRs are reviewed and merged.