Week 7
(July 15, 2025 – July 21, 2025)
Meeting 7
(July 18, 2025)
Attendees
Discussions
- Walked through heartbeat implementation and memory-aware parallelization logic.
- Discussed challenges with SIGTERM signal handling for agent cancellation.
- Shaheem shared helpful documentation on process signal handling strategies in Python.
- Reviewed improvements in process management and configuration defaults.
Updates
- Heartbeat functionality is now fully integrated and working as intended for all worker processes.
- Removed hardcoded memory limit configuration.
- Implemented a dynamic adjustment mechanism that reduces the number of worker processes based on available system memory.
- Lowered the default number of parallel jobs to a safer.
- Began work on capturing
SIGTERM
to cleanly shut down all worker processes when the agent is canceled. - Facing some technical challenges in implementation—discussed with Shaheem and received relevant documentation for further debugging.
Plan for Next Week
- Finalize and fully implement shutdown behavior when a user cancels the agent (SIGTERM handling).
- Ensure job status and disclaimers are properly reflected in the Job View UI.