Week 8
(July 22, 2025 – July 28, 2025)
Meeting 8
(July 25, 2025)
Attendees
Discussions
- Confirmed that thread shutdown now works correctly when a user cancels the agent.
- Reviewed heartbeat logging enhancements and added ETA .
- Discussed current inconsistencies in the FOSSology Dump mechanism.
- Jan advised testing of the dump system to help identify bugs.
Updates
- Finalized SIGTERM capture logic; worker processes now gracefully stop when the agent is cancelled.
- Improved heartbeat log structure for better traceability.
- Began preliminary testing of the FOSSology Dump system to identify existing issues.
- Jan pointed out that some bugs might be affecting reports.
Plan for Next Week
- Conduct thorough testing of all PRs made up to this point.
- Continue testing and investigation into the FOSSology Dump system to help identify potential bugs.