Week 11 Meetings and Activities

Project Sync Meeting 12

(August 12, 2025)

Attendees

Discussion

  • Showed mentors the progress in the implementation of the redesigned components and pages.
  • Completed implementing the redesigned Schedule an Analysis page.
  • Installed and configured required shadcn components (Tooltip, Select, Label, Sonner and Checkbox) to support the redesign.

FOSSology GSoC Weekly Meet

(August 14, 2025)

Attendees:

Missed:

Discussion

Mentors

Contributors

  • Tiyasa Kundu

    • Shared Week 11 progress with the community, showcasing the completion of the implementation of the Schedule an Analysis Page.
    • Mentioned about the WIP Pull Request #328 openend and the commit made with the code for the implemented Schedule an Analysis Page (commit link).
  • Other Contributors

    • Each contributor briefly shared their weekly progress and updates.

Activities Done in Week 11

  • Implemented the redesigned Schedule an Analysis Page.
  • Installed and configured additional shadcn components (Tooltip, Select, Label, Sonner and Checkbox) to support the redesign.
  • Demonstrated progress on redesigned components and pages to mentors, highlighting the completion of the Schedule an Analysis Page implementation.
  • Opened a WIP Pull Request #328 and committed the code for the implemented components.

Progress Demo

  • Redesigned Schedule an Analysis Page:

alt text

Next Steps

  • Continue implementing other redesigned components and pages as per the redesigned UI mockups.